Live view from Howe Hall

Video Poster

Live view from Beyer Hall

Video Poster

March 2024

  • Installation of level 4 piping, shaft pipe stack clamps/anchor points, level 4 mechanical room rough-ins, level 4 plumbing/heating piping
  • Installation of level 3 VAVs and rough-ins, duct insulation, level 4 duct work
  • Start installation of punched windows, set curtain wall glass, air barrier for punched windows
  • Installation of lightning protection ground rods, basement level in-wall rough-ins, level 2 wire pulls and AV floor boxes, overhead rough-in/fire alarm conduit
  • Installation of level 1 and 3 floor/wall/door framing, level 1 vestibule framing, level 4 top outs, level 2 and 3 bathroom framing, level 3 shaft wall framing, level 4 framing

 

February 2024

  • Installation of basement and level 3 piping, equipment tie-ins/connections, steam tie-ins/connections, shaft pipe stack clamps/anchor points
  • Installation of level 3 duct/rough-ins, duct insulation, steam traps, VAVs
  • Completion of water/air barrier, Installation of curtain wall, foundation trench for installation of precast panels, set curtain wall frames
  • Installation of level 2 and 3 wall conduit, level 4 hangers/supports, basement and level 3 cable trays, lightning protection, level 2 feeder run
  • Installation of bulkhead framing, level 1 and 4 floor grinding/floor protection, door frame blocking, level 3 floor/wall framing, level 1/vestibule framing
  • Installation of elevator shaft motors

 

Therkildsen IE building construction, man working on concrete with orange curtains in background

January 2024

  • Installation of overhead duct work/rough-ins and duct insulation at level 3, VAV tie-ins at level 2
  • Installation of wall electrical conduit at level 2 and 3, overhead electrical conduit and rough-ins at level 3
  • Installation of plumbing piping at basement, level 2, and level 3, storm piping at level 3 and 4
  • Installation of interior framing at basement, level 1, and level 3
  • Grind level 3 floor and install floor protection
  • Installation of exterior metal panels at level 1 and 2
  • Firestopping installation at level 1
  • Begin installation of roofing

 

People in safety gear touring the Therkildsen Building construction site.

December 2023

  • Installation of level 3 partition supports
  • Installation of overhead duct work/rough-ins on level 2
  • Installation of overhead and wall electrical conduit on level 2
  • Installation of plumbing piping at basement and level 2
  • Installation of interior framing on levels 1 and 2
  • Firestopping installation at level 3
  • Temporary enclosure of exterior for heating, Installation of exterior metal panels at level 1
  • Strobic exhaust fan delivery
drone view of Therkildsen Industrial Engineeering building construction

November 2023

  • Concrete stair pans
  • Auditorium slab pours in progress
  • Preparation of temporary gas line for building heat during construction
  • Spray fire protection in progress for structure
  • Floor protection installation for poured areas in progress
  • Hanger installation in progress
  • Domestic Water tie in to Thielen complete
  • Preparing for AHU delivery, expect to crane to 4th floor
  • Building utility tie-ins from the south in progress
  • Prep for installation of air barrier/formed metal panels in progress
drone view of Therkildsen Industrial Engineering building construction
drone view of Therkildsen Industrial Engineering building construction

October 2023

  • Steel frame structure erected
  • Metal decking installed
  • East side underground work complete
  • Hangers/sleeve installation in progress
  • Embeds/sleeve installation in progress
  • Removal of basement bracing
  • Building utility tie-ins in progress
drone view of Therkildsen Industrial Engineering construction
drone view of Therkildsen Industrial Engineering building construction

August 2023

  • Steel erection in progress
  • Central core precast concrete panel work in progress (shown below)
  • East and west stair precast concrete panel work in progress
  • Underground storm precast work in progress
crane handling building components on Therkildsen Industrial Engineering building construction site

July 2023

  • Basement slab and backfill are complete
  • Construction on the electrical vault and installation of the stormwater detention system are in progress
  • Installation of the precast concrete panels is set to begin
  • Concrete work on Sheldon Avenue and Parking Lot 10 is complete; installation of retaining walls and lighting is now in progress

June 2023

drone view of Therkildsen Industrial Engineering building construction

May 2023

  • Backfill for the elevator pit is now in progress
  • Steam vault construction has begun
  • Installation of formwork and pours for basement footings and walls continues (shown below)
Therkildsen Industrial Engieering building construction
Therkildsen Industrial Engieering building construction

April 2023

  • Chilled water line connection to Thielen is in progress
  • Excavation and installation of formwork for basement footings continues

March 2023

  • Excavation for basement footings is in progress, including the elevator pit
  • Chilled water line connection to Thielen in progress
  • Installation of aggregate piers complete
  • Backfilling for chilled water line work in progress
  • Shoring in place to support existing duct bank
foundation preparation begins

February 2023

  • Site work on chilled water lines continues
  • Preparation for installation of aggregate piers in progress
  • Shoring for existing underground telecom duct bank in progress
  • Sanitary sewer work on the site continues
  • Sewer tie-ins to Howe Hall and Thielen Student Health Center are complete

January 2023

  • Site is turned over to Story Construction
  • Perimeter fencing installed, job trailers set up, and concrete demolition in progress
concrete demolition begins with heavy equipment
concrete demolition begins with heavy equipment
concrete demolition begins with heavy equipment
concrete demolition begins with heavy equipment
concrete demolition begins with heavy equipment