Construction Progress
Live view from Howe Hall:
Live view from Beyer Hall:
August 2023
- Steel erection in progress
- Central core precast concrete panel work in progress (see attached photo taken 08/15/23)
- East and west stair precast concrete panel work in progress
- Underground storm precast work in progress

July 2023
- Basement slab and backfill are complete
- Construction on the electrical vault and installation of the stormwater detention system are in progress
- Installation of the precast concrete panels is set to begin
- Concrete work on Sheldon Avenue and Parking Lot 10 is complete; installation of retaining walls and lighting is now in progress
June 2023

February 2023
- Site work on chilled water lines continues
- Preparation for installation of aggregate piers in progress
- Shoring for existing underground telecom duct bank in progress
- Sanitary sewer work on the site continues
- Sewer tie-ins to Howe Hall and Thielen Student Health Center are complete